During the Managing a Stage Boundary process, the Project Manager produces an Exception Plan. What triggers this?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The stage is forecast to exceed its tolerance

An Exception Plan is produced when a stage is forecast to exceed its tolerances, as an alternative to the current Stage Plan, for approval by the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    The stage is forecast to exceed its tolerance

    Why this is correct

    Forecast tolerance breach during a stage is the trigger: the Project Manager must escalate via an Exception Report, and once the board approves, an Exception Plan replaces the remainder of the Stage Plan. This satisfies the Managing a Stage Boundary requirement to replan the current stage when its tolerances can no longer be met.

  • ✗

    A Team Manager reports a delay in the Work Package

    Why it's wrong here

    A Work Package delay is handled by the Team Manager within tolerance, escalating only if the Work Package tolerance is forecast to be exceeded; an Exception Plan follows a Stage Plan or Project Plan exception. It is tempting because Work Package status accounts are the usual source of progress data during a stage.

  • ✗

    The Project Board requests a new plan for the next stage

    Why it's wrong here

    A new plan for the next stage is produced routinely within Managing a Stage Boundary, not as an Exception Plan. It is tempting because the Project Board does request plans, and would be correct if the stage were forecast to exceed its tolerances, triggering exception handling.

  • ✗

    The Project Manager decides to change the project approach

    Why it's wrong here

    An Exception Plan responds to a Project Board decision following a forecast breach of stage tolerances, not to the Project Manager unilaterally changing the approach. It is tempting because the Project Manager does author plans, and would be correct if the change were escalated and approved through change control.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.