Which TWO of the following are correct statements about tolerance in PRINCE2?
⚠ Common exam trap
A common misconception is that tolerances apply only to time and cost, but PRINCE2 explicitly includes scope, quality, risk, and benefits as additional tolerance dimensions.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Project Board sets stage tolerances for the Project Manager
In PRINCE2, the Project Board sets stage tolerances for the Project Manager as part of the 'Manage by Stages' principle. This allows the Project Manager to manage the stage within defined tolerances without needing to escalate every minor deviation, ensuring delegated authority is clear and controlled.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The Project Board sets stage tolerances for the Project Manager
Why this is correct
The Board delegates authority via stage tolerances.
- ✓
If a stage tolerance is exceeded, the Project Manager must escalate
Why this is correct
Exceeding tolerance requires an Exception Report.
- ✗
Tolerances apply only to time and cost
Why it's wrong here
Tolerances also apply to scope, quality, risk, and benefits.
- ✗
The Project Manager can never change tolerances without Board approval
Why it's wrong here
Within a stage, the PM can reallocate tolerance between activities as long as the overall stage tolerance is not exceeded.
- ✗
Tolerances are set only at project level
Why it's wrong here
Tolerances are set at project and stage levels.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.