Courseiva
PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Which report does the Project Manager produce regularly to inform the Project Board of progress within a stage?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Highlight Report

The Highlight Report is produced by the Project Manager at intervals defined in the Communication Management Approach to update the Project Board on progress.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Highlight Report

    Why this is correct

    The Highlight Report is produced by the Project Manager at agreed intervals to inform the Project Board of progress, status and issues within the current stage. This directly satisfies the stem's requirement for a regular progress report during a stage.

  • ✗

    End Stage Report

    Why it's wrong here

    The End Stage Report is produced at the conclusion of a stage to review performance and request authorisation for the next, not regularly during it. It is tempting because it does inform the Project Board, and it would be correct at a stage boundary rather than for ongoing progress reporting.

  • ✗

    Checkpoint Report

    Why it's wrong here

    Checkpoint Reports flow from Team Managers to the Project Manager at agreed frequencies, covering team-level progress, not stage-level reporting to the Project Board. They are tempting because they are genuinely regular progress reports, but the wrong sender and recipient; the Highlight Report is the Project Manager's stage report.

  • ✗

    Exception Report

    Why it's wrong here

    Exception Reports are produced only when tolerances are forecast to be exceeded, so they cannot provide routine in-stage progress updates. They are tempting because they do inform the Project Board, but of deviations rather than regular progress; the Highlight Report serves that recurring purpose.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.