Which report does the Project Manager produce regularly to inform the Project Board of progress within a stage?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Highlight Report
The Highlight Report is produced by the Project Manager at intervals defined in the Communication Management Approach to update the Project Board on progress.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Highlight Report
Why this is correct
The Highlight Report is sent from the Project Manager to the Project Board.
- ✗
End Stage Report
Why it's wrong here
The End Stage Report is produced at the end of a stage.
- ✗
Checkpoint Report
Why it's wrong here
The Checkpoint Report is produced by Team Managers for the Project Manager.
- ✗
Exception Report
Why it's wrong here
The Exception Report is produced when tolerances are forecast to be exceeded.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.