Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

What is the difference between a Request for Change and an Off-specification?

⚠ Common exam trap

Test-takers frequently confuse the source of the issue (who raises it) or the register it belongs to, when the core distinction is the nature of the problem—proposing a change versus reporting a failure to meet a specification.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

A Request for Change proposes a modification to baselined products; an Off-specification identifies a failure to meet a specification

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify a baselined product, while an Off-specification (Off-spec) is a notification that a product does not meet its agreed specification. The key distinction is that an RFC seeks to change the specification itself, whereas an Off-spec reports a failure to conform to the existing specification. Option B correctly captures this fundamental difference.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • A Request for Change always requires a change budget; an Off-specification does not

    Why it's wrong here

    Both may require a change budget, but that is not the defining difference.

  • A Request for Change proposes a modification to baselined products; an Off-specification identifies a failure to meet a specification

    Why this is correct

    This is the correct distinction: RFC proposes a change, Off-specification identifies a deviation.

  • A Request for Change is raised by the Project Board; an Off-specification is raised by the Project Manager

    Why it's wrong here

    Both can be raised by anyone, but the key difference is the nature of the issue.

  • A Request for Change is recorded in the Risk Register; an Off-specification is recorded in the Issue Register

    Why it's wrong here

    Both are recorded in the Issue Register.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.