In which process are Highlight Reports produced and sent to the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Controlling a Stage

Highlight Reports are produced by the Project Manager during the Controlling a Stage process and sent to the Project Board to provide a summary of progress.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary produces End Stage Reports.

  • Directing a Project

    Why it's wrong here

    Directing a Project receives Highlight Reports but does not produce them.

  • Managing Product Delivery

    Why it's wrong here

    Managing Product Delivery produces Checkpoint Reports, not Highlight Reports.

  • Controlling a Stage

    Why this is correct

    Correct. The PM produces Highlight Reports in Controlling a Stage.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.