In which process are Highlight Reports produced and sent to the Project Board?

⚠ Common exam trap

PRINCE2F often tests the difference between Highlight Reports (Controlling a Stage) and End Stage Reports (Managing a Stage Boundary) — candidates frequently mix up which process produces which report.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Controlling a Stage

Highlight Reports are produced by the Project Manager and sent to the Project Board during the 'Controlling a Stage' process. This process includes the activity 'Report Highlights,' where the Project Manager summarizes stage progress, issues, and risks for the Board's information and direction.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary produces the End Stage Report for the Board at stage closure, not the periodic Highlight Report. It is tempting because it also generates Board-facing documentation, and would be correct when seeking a decision to authorise the next stage.

  • ✗

    Directing a Project

    Why it's wrong here

    Directing a Project covers the Project Board's own decisions and controls, not the production of Highlight Reports, which flow upward from the managing level. It is tempting because the Board receives these reports, and would be correct when describing the Board's authorisation of stage or project progression.

  • ✗

    Managing Product Delivery

    Why it's wrong here

    Managing Product Delivery concerns the work of teams producing products and accepting them, not reporting progress to the Project Board. It is tempting because it is a delivery-focused process, and would be correct for controlling the interface between the project manager and team managers.

  • ✓

    Controlling a Stage

    Why this is correct

    Controlling a Stage is where the Project Manager monitors progress, takes corrective action and produces Highlight Reports for the Project Board at the agreed frequency. This satisfies the stem's requirement for the process that generates and sends them.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.