PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are outputs of the Initiating a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Benefits Management Approach
The PID and the Benefits Management Approach are key outputs of IP. The Project Brief is from SU, and the Work Package is from CS or MP.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
End Stage Report
Why it's wrong here
End Stage Report is an output of Managing a Stage Boundary.
- ✓
Benefits Management Approach
Why this is correct
The Benefits Management Approach is created during Initiating a Project.
- ✗
Work Package
Why it's wrong here
Work Packages are authorised in Controlling a Stage and delivered in Managing Product Delivery.
- ✓
Project Initiation Documentation
Why this is correct
The PID is the key output of Initiating a Project.
- ✗
Project Brief
Why it's wrong here
The Project Brief is an output of Starting Up a Project, not Initiating a Project.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.