A project team is about to begin the first stage of a project. The project board has approved the project initiation documentation. Which process should be used to authorize the work?

⚠ Common exam trap

Candidates often confuse the process that creates the PID (Initiating a Project) with the process that authorizes the first stage (Directing a Project). The project board, not the project manager, authorizes the first stage via Directing a Project. Starting Up a Project only compiles the project brief and plans the initiation stage; it does not authorize any stages.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

After the PID is approved, the project board authorizes the work for the first stage via the Directing a Project process, specifically the 'Authorize the project' activity. This process provides the necessary authorization for the project manager to start the first stage. Initiating a Project produces the PID, but authorization to proceed is given by the project board through Directing a Project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Starting Up a Project

    Why it's wrong here

    Starting Up a Project is the pre-project process, not used for authorizing work after PID approval.

  • Managing Product Delivery

    Why it's wrong here

    Managing Product Delivery controls the link between the project manager and team managers for work package delivery, but the initial authorization comes from Initiating a Project.

  • Directing a Project

    Why this is correct

    Directing a Project authorizes the overall project, not the specific work in the first stage.

  • Initiating a Project

    Why it's wrong here

    Initiating a Project includes the creation and approval of the PID, which authorizes the work for the first stage.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.