Which TWO of the following are components of the Project Initiation Documentation (PID)?

⚠ Common exam trap

Candidates often confuse the Project Brief as a component of the PID, but it is actually a predecessor document that is superseded by the PID during the Initiating a Project process.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Business Case

The Business Case is a core component of the Project Initiation Documentation (PID) because it provides the justification for the project, including costs, benefits, and risks. The Project Plan is also a component of the PID as it defines how and when the project objectives will be achieved, including timescales and resource requirements. Both are mandatory elements that form the foundation of the PID in PRINCE2.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Brief

    Why it's wrong here

    The Project Brief is an input to the PID but not a component of it.

  • Business Case

    Why this is correct

    The Business Case is a core component of the PID.

  • Project Plan

    Why this is correct

    The Project Plan is a mandatory component of the Project Initiation Documentation (PID) because it defines the detailed timing, cost, and resource baselines required to execute the project. In the PRINCE2 framework, the PID must contain the Project Plan to satisfy the "plans" theme, which demands a baseline against which progress is measured. Without this plan, the PID cannot provide the authorised scope and schedule needed for controlled project delivery.

  • Checkpoint Report

    Why it's wrong here

    The Checkpoint Report is a progress report, not part of the PID.

  • Project Product Description

    Why it's wrong here

    The Project Product Description is a separate product; not a component of the PID.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are components of the Project Initiation Documentation (PID)?

medium
  • A.The Project Plan
  • B.The Stage Plan
  • C.The Exception Plan
  • D.The Team Plan
  • E.The Business Case

Why A: The Project Initiation Documentation (PID) is a key PRINCE2 management product that provides a foundation for the project. The Project Plan is a core component of the PID as it defines the overall timeline, costs, and resources for the entire project. The Business Case is also a mandatory component, providing the justification for the project and ensuring its continued viability.

Variation 2. Which TWO of the following are components of the Project Initiation Documentation (PID)?

medium
  • A.Lessons Log
  • B.Business Case
  • C.Issue Register
  • D.Project Plan
  • E.Risk Register

Why B: The PID includes the Project Plan and the Business Case. The Risk Register and Issue Register are separate documents. The Lessons Log is created during Starting Up a Project.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.