Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which role is responsible for providing assurance that the project is being managed correctly in terms of business, user, and supplier interests?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Assurance

Project Assurance is an independent role that provides assurance to the Project Board on all three interests (business, user, supplier). Option A is incorrect because Project Support provides administrative support, not independent assurance. Option B is incorrect because the Project Manager is responsible for day-to-day management, not independent assurance. Option C is incorrect because the Team Manager is responsible for delivering work packages, not providing assurance across interests.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Support

    Why it's wrong here

    Project Support provides administrative services, not independent assurance.

  • Project Manager

    Why it's wrong here

    The Project Manager is tasked with day-to-day management of the project, not with independent assurance. The PRINCE2 principle of defined roles and responsibilities separates management from assurance; the Project Manager cannot provide objective assurance over their own work. This option tempts because the Project Manager oversees all three interests (business, user, supplier) operationally, but the role lacks the independence required to verify that management itself is correct. The correct choice is the Project Assurance role, which is explicitly assigned to provide this independent check.

  • Team Manager

    Why it's wrong here

    The Team Manager focuses on the technical delivery of work packages within a stage, not on providing independent assurance across business, user, and supplier interests. This role is tempting because it oversees the team’s daily work, but assurance is a distinct function assigned to the Project Assurance role, which checks compliance with the project’s management controls from each stakeholder perspective.

  • Project Assurance

    Why this is correct

    Project Assurance provides independent oversight of the project's management.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.