PRINCE2F PRINCE2 Processes Practice Question
A Work Package is authorized by the Project Manager. In which process does this happen?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Controlling a Stage
Authorizing Work Packages is an activity in the Controlling a Stage process, where the PM assigns work to Team Managers.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Controlling a Stage
Why this is correct
CS includes authorizing Work Packages.
- ✗
Managing Product Delivery
Why it's wrong here
MP involves accepting and delivering Work Packages, not authorizing them.
- ✗
Directing a Project
Why it's wrong here
DP does not authorize Work Packages; that is the PM's role.
- ✗
Starting Up a Project
Why it's wrong here
SU does not involve Work Packages.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.