Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A Work Package is authorized by the Project Manager. In which process does this happen?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Controlling a Stage

Authorizing Work Packages is an activity in the Controlling a Stage process, where the PM assigns work to Team Managers.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Controlling a Stage

    Why this is correct

    CS includes authorizing Work Packages.

  • Managing Product Delivery

    Why it's wrong here

    MP involves accepting and delivering Work Packages, not authorizing them.

  • Directing a Project

    Why it's wrong here

    DP does not authorize Work Packages; that is the PM's role.

  • Starting Up a Project

    Why it's wrong here

    SU does not involve Work Packages.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.