PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

A Work Package is authorized by the Project Manager. In which process does this happen?

⚠ Common exam trap

PRINCE2F often tests the distinction between who authorizes a Work Package (Project Manager, in Controlling a Stage) versus who accepts and executes it (Team Manager, in Managing Product Delivery) — candidates frequently swap these two processes.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Controlling a Stage

In PRINCE2, the Project Manager authorizes Work Packages during the 'Controlling a Stage' process. This is where the Project Manager manages day-to-day stage activities, including authorizing work, monitoring progress, and taking corrective action. The Work Package is the agreed description of work to be produced by the Team Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Controlling a Stage

    Why this is correct

    Controlling a Stage is where the Project Manager authorises Work Packages, confirming the work, tolerances and reporting requirements before the team manager proceeds. This satisfies the stem's constraint that authorisation occurs during stage execution, not during initiation or planning, where products and stage plans are instead defined and agreed.

  • ✗

    Managing Product Delivery

    Why it's wrong here

    Authorising a Work Package occurs in Directing a Project, where the Project Board approves the stage plan and the Project Manager issues the Work Package; Managing Product Delivery only accepts and executes it. Tempting because Managing Product Delivery handles Work Package agreement, but that is acceptance by the Team Manager, not authorisation.

  • ✗

    Directing a Project

    Why it's wrong here

    Directing a Project is where the Project Board authorises the project and stage boundaries, not individual Work Packages. It is tempting because that process does grant formal approval to proceed, but its authorisations are stage-level decisions made by the Board. Work Package authorisation sits with the Project Manager in Controlling a Stage.

  • ✗

    Starting Up a Project

    Why it's wrong here

    Starting Up a Project covers pre-project activities such as appointing the Executive and preparing the Project Brief, before any Work Package exists. It would be correct if the question concerned appointing the Project Manager or assembling the initiation documentation.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.