Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A project is in the Managing a Stage Boundary process. Which TWO outputs are produced during this process? (Select TWO)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

End Stage Report

SB produces the End Stage Report and the next Stage Plan (or Exception Plan).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Plan

    Why it's wrong here

    The Project Plan is updated but not first produced in SB; it is produced in IP and updated in SB.

  • Benefits Management Approach

    Why it's wrong here

    Benefits Management Approach is produced in IP.

  • End Stage Report

    Why this is correct

    Yes, the End Stage Report summarises the current stage.

  • Project Brief

    Why it's wrong here

    Project Brief is produced in SU.

  • Next Stage Plan

    Why this is correct

    Yes, the next Stage Plan is produced for Board approval.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

6 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project is in the Managing a Stage Boundary process. Which of the following is produced during this process?

hard
  • A.Exception Report
  • B.End Stage Report
  • C.Highlight Report
  • D.Project Brief

Why B: The End Stage Report is produced to report on the current stage's performance.

Variation 2. A project is in the Managing a Stage Boundary process. The Project Manager identifies a deviation that will cause the stage to exceed its tolerance. What should the Project Manager produce?

hard
  • A.Exception Plan
  • B.End Stage Report
  • C.Exception Report
  • D.Lessons Report

Why A: If a tolerance is forecast to be exceeded during a stage, the PM should have already escalated via an Exception Report in Controlling a Stage. However, if this is identified during Managing a Stage Boundary, the PM should still produce an Exception Plan for the Board's approval.

Variation 3. A project is in the Managing a Stage Boundary process. The Project Manager has produced an End Stage Report. What else must be produced?

hard
  • A.Benefits Review Plan
  • B.Stage Plan for the next stage
  • C.Project Initiation Documentation
  • D.Project Brief

Why B: In the Managing a Stage Boundary process, the Project Manager produces an End Stage Report to summarize the current stage's performance. The PRINCE2 method requires that a Stage Plan for the next stage must also be produced during this process, as it provides the detailed plan for the upcoming work and is essential for the Project Board to authorize the next stage. Without the next Stage Plan, the project cannot proceed beyond the current stage boundary.

Variation 4. A Project Manager is in the Managing a Stage Boundary process and has produced the End Stage Report. The project is forecasting to exceed the project-level cost tolerance. What must the PM include in the next Stage Plan?

hard
  • A.No Stage Plan; the project must be escalated immediately
  • B.A request to close the project
  • C.An Exception Plan that outlines the corrective actions and revised tolerances
  • D.A normal Stage Plan, but with additional cost contingencies

Why C: If project-level tolerance is forecast to be exceeded, an Exception Plan is required instead of a normal Stage Plan. The Exception Plan must be approved by the Project Board.

Variation 5. In the Managing a Stage Boundary process, what is produced to request permission to proceed to the next stage?

hard
  • A.Benefits Review Plan
  • B.Next Stage Plan
  • C.Project Brief
  • D.Exception Report

Why B: The End Stage Report and next Stage Plan are produced; the Project Board then decides in DP.

Variation 6. In the Managing a Stage Boundary process, the Project Manager updates the Project Plan. What is the main purpose of this update?

hard
  • A.To reflect the actual progress and re-forecast the remaining work
  • B.To provide a baseline for performance measurement
  • C.To replace the original Project Plan entirely
  • D.To create a detailed plan for the next stage only

Why A: The Project Plan is updated to reflect the actual progress of the completed stage and to provide a realistic baseline for the remaining stages. This helps the Project Board make an informed decision about whether to proceed with the next stage.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.