Courseiva
Project Initiation and StageseasyMultiple ChoiceObjective-mapped

PRINCE2F Project Initiation and Stages Practice Question

During the Initiating a Project process, the project manager identifies that the business case relies on a key supplier delivering critical components by a fixed date. However, the supplier has a history of delays. What should the project manager do?

⚠ Common exam trap

PeopleCert often tests the misconception that a risk can be handled informally or deferred to later stages, but PRINCE2 requires formal recording and planning of risks during the Initiating a Project process to ensure they are managed from the start.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Record the risk in the risk register and plan a response in the risk management approach

In PRINCE2, the risk register is the central repository for recording all identified risks, and the risk management approach defines how risks will be managed throughout the project. During the Initiating a Project process, the project manager must formally document the supplier delay risk and plan appropriate responses (e.g., mitigation, contingency) within the risk management approach. This ensures the risk is actively managed rather than ignored or deferred, aligning with PRINCE2's principle of continued business justification.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Proceed with the plan as the supplier has always delivered eventually

    Why it's wrong here

    Ignoring a known risk is not PRINCE2 best practice.

  • Adjust the business case to remove the supplier dependency

    Why it's wrong here

    Changing the business case requires formal change control.

  • Ask the project board to approve the project with a note about the risk

    Why it's wrong here

    The project board should be informed, but the risk must be formally recorded.

  • Record the risk in the risk register and plan a response in the risk management approach

    Why this is correct

    Risks must be formally recorded and managed.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During the Initiation Stage, the project manager identifies that the selected team lacks experience with the chosen technology. What should the project manager do?

medium
  • A.Replace the team members with experienced ones
  • B.Escalate to the Project Board for decision
  • C.Update the Project Plan to include training
  • D.Update the Risk Register and plan a response

Why D: The lack of experience with the chosen technology is a risk to the project, not an immediate issue. During the Initiation Stage, the project manager should formally record this risk in the Risk Register and plan an appropriate response, such as training or mentoring, to manage the uncertainty. This aligns with PRINCE2's principle of managing by stages and the requirement to identify and respond to risks proactively.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.