Courseiva
Business Case and OrganizingmediumMultiple ChoiceObjective-mapped

PRINCE2F Business Case and Organizing Practice Question

You are the project manager for a software development project. The business case shows a net present value (NPV) of $200,000 with a payback period of 18 months. During the initiating stage, the senior supplier informs you that the cost of a key component has increased by 20%, which will reduce the NPV to $50,000 and extend the payback period to 24 months. The project board is not scheduled to meet for another month. What should you do?

⚠ Common exam trap

PeopleCert often tests the misconception that the project manager can autonomously adjust the business case or scope to fix issues, when in fact PRINCE2 mandates escalation to the project board for any significant deviation from the approved plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Request an extraordinary meeting of the project board to discuss the revised business case

PRINCE2 requires that any change to the business case, especially one that significantly reduces NPV and extends payback period, must be escalated to the project board for a decision. As project manager, you cannot unilaterally update the business case or change scope; you must request an extraordinary meeting to present the revised business case and seek approval to continue. This aligns with the 'continued business justification' principle and the 'manage by stages' theme.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Request an extraordinary meeting of the project board to discuss the revised business case

    Why this is correct

    Correct: escalate immediately for decision.

  • Update the business case with the new figures and continue with the project

    Why it's wrong here

    The business case must be approved by the board; unauthorized changes are not allowed.

  • Reduce project scope to bring costs back in line with the original business case

    Why it's wrong here

    Scope changes require board approval.

  • Wait for the next scheduled board meeting to present the changes

    Why it's wrong here

    Delaying could lead to wasted effort; immediate escalation is needed.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a project, the cost-benefit ratio becomes unfavorable. What is the first action the project manager should take?

hard
  • A.Update the Business Case without informing the board
  • B.Reduce project scope to cut costs
  • C.Stop the project immediately
  • D.Request a formal review of the Business Case by the project board

Why D: In PRINCE2, the Business Case is the key document for justifying the project's continued viability. When the cost-benefit ratio becomes unfavorable, the project manager must escalate this issue to the project board, which holds the authority to approve changes to the Business Case or decide on project continuation. Option D is correct because the project manager's first action is to request a formal review by the project board, as per the 'continued business justification' principle and the 'manage by stages' theme.

Variation 2. During a project, the senior user requests a change that significantly increases benefits but also increases costs. What should the project manager do first?

hard
  • A.Implement the change immediately to realize benefits quickly
  • B.Update the Business Case and proceed without approval
  • C.Reject the change because it increases costs
  • D.Assess the impact on the Business Case and submit a change request to the project board

Why D: In PRINCE2, any change that impacts the Business Case must be formally assessed before action is taken. The project manager's first responsibility is to evaluate the change's effect on the Business Case (costs vs. benefits) and then submit a formal change request to the Project Board, which holds authority for approving changes that alter the project's justification. Option D aligns with the 'manage by stages' and 'continued business justification' principles.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.