During which process are Work Packages authorised by the Project Manager?

⚠ Common exam trap

The trap is confusing the authorization of Work Packages with the acceptance of Work Packages. Candidates may think Managing Product Delivery authorizes Work Packages, but it only accepts and executes them.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Controlling a Stage

Work Packages are authorized by the Project Manager within the Controlling a Stage process. In this process, the Project Manager assigns work to the Team Manager by creating and authorizing Work Packages, which include the required products, constraints, and reporting requirements. This is a core activity of Controlling a Stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Directing a Project

    Why it's wrong here

    Directing a Project covers the Project Board's decisions — authorising the project, stage or closure — not the issue of Work Packages to Team Managers. Work Package authorisation belongs to Controlling a Stage, where the Project Manager agrees delivery with the team.

  • ✓

    Controlling a Stage

    Why this is correct

    Work Packages are authorised by the Project Manager during Controlling a Stage, where agreed work is delegated to the Team Manager and progress monitored against the Stage Plan. Managing Product Delivery receives and executes those Work Packages, but authorisation itself occurs in Controlling a Stage.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary produces the End Stage Report and Next Stage Plan for the Project Board's approval, so it concerns stage-level authority, not individual Work Packages. Work Packages are authorised in Controlling a Stage, once the stage plan and tolerances are already agreed.

  • ✗

    Managing Product Delivery

    Why it's wrong here

    Managing Product Delivery is the Team Manager's process: accepting, executing and delivering a Work Package, then reporting completion. The Project Manager authorises the Work Package in Controlling a Stage; this process receives it, so the direction of authorisation is reversed.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.