PRINCE2F PRINCE2 Processes Practice Question
During the Controlling a Stage process, who receives the Highlight Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The Highlight Report is produced by the Project Manager and sent to the Project Board to provide a summary of stage progress.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Support
Why it's wrong here
Project Support may assist in preparing the report but is not the recipient.
- ✗
Team Manager
Why it's wrong here
The Team Manager receives Checkpoint Reports, not Highlight Reports.
- ✓
Project Board
Why this is correct
Highlight Reports are sent to the Project Board as part of management by exception.
- ✗
Senior User
Why it's wrong here
The Senior User is a member of the Project Board, but the report goes to the entire Board.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.