Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During the Controlling a Stage process, who receives the Highlight Report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board

The Highlight Report is produced by the Project Manager and sent to the Project Board to provide a summary of stage progress.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Support

    Why it's wrong here

    Project Support may assist in preparing the report but is not the recipient.

  • Team Manager

    Why it's wrong here

    The Team Manager receives Checkpoint Reports, not Highlight Reports.

  • Project Board

    Why this is correct

    Highlight Reports are sent to the Project Board as part of management by exception.

  • Senior User

    Why it's wrong here

    The Senior User is a member of the Project Board, but the report goes to the entire Board.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.