Courseiva
PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

During the Controlling a Stage process, who receives the Highlight Report?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

The Highlight Report is produced by the Project Manager and sent to the Project Board to provide a summary of stage progress.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative assistance and maintains logs and registers; it does not receive Highlight Reports as a recipient. The report is sent to the Project Board, so this option confuses a support function with the governance body that consumes progress information during Controlling a Stage.

  • ✗

    Team Manager

    Why it's wrong here

    The Highlight Report is produced by the Project Manager for the Project Board, not the Team Manager, who receives Work Packages and issues Checkpoint Reports upward. Team Managers are tempting because they report progress during Controlling a Stage, but that reporting flows in the opposite direction.

  • ✓

    Project Board

    Why this is correct

    The Highlight Report is produced by the Project Manager during Controlling a Stage and sent to the Project Board, keeping it informed of stage progress, issues and forecast. This satisfies the stem's question about the report's recipient.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User sits on the Project Board, which receives Highlight Reports collectively; singling out the Senior User misstates the distribution. The report goes to all Project Board members, so naming one role as recipient misidentifies the reporting line defined in Controlling a Stage.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.