Drag steps to the numbered slots on the right, or tap a step then tap a slot.
PRINCE2F PRINCE2 Practices Practice Question
Drag and drop the steps to create a PRINCE2 project plan into the correct order.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Step 1: Design the plan, Step 2: Define and analyze products, Step 3: Identify activities and dependencies, Step 4: Estimate, Step 5: Schedule and document the plan
Planning steps: design the plan, define products, identify activities, estimate, and schedule/document.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Step 1: Design the plan, Step 2: Define and analyze products, Step 3: Identify activities and dependencies, Step 4: Estimate, Step 5: Schedule and document the plan
Why this is correct
This is the correct order as per PRINCE2 planning steps. Designing the plan establishes scope and approach, then defining products identifies what needs to be created, followed by identifying activities to build those products, estimating effort and duration, and finally scheduling and documenting the plan.
- ✗
Step 1: Define and analyze products, Step 2: Design the plan, Step 3: Identify activities and dependencies, Step 4: Estimate, Step 5: Schedule and document the plan
Why it's wrong here
This is incorrect because defining products should come after designing the plan, as the plan design sets the overall context and approach before detailing specific products.
- ✗
Step 1: Design the plan, Step 2: Identify activities and dependencies, Step 3: Define and analyze products, Step 4: Estimate, Step 5: Schedule and document the plan
Why it's wrong here
This is incorrect because identifying activities should be based on the products that need to be created, so defining products must come before identifying activities.
- ✗
Step 1: Design the plan, Step 2: Define and analyze products, Step 3: Estimate, Step 4: Identify activities and dependencies, Step 5: Schedule and document the plan
Why it's wrong here
This is incorrect because estimating effort and duration requires knowing the activities involved, so estimating should come after identifying activities, not before.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.