In the Organising practice, which role is responsible for providing assurance that the project is being conducted correctly?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Assurance
Project Assurance is independent of the Project Manager and provides assurance to the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team Manager
Why it's wrong here
Team Managers are responsible for delivering work packages.
- ✓
Project Assurance
Why this is correct
Project Assurance is independent and provides objective oversight.
- ✗
Project Support
Why it's wrong here
Project Support provides administrative services.
- ✗
Project Manager
Why it's wrong here
The Project Manager is responsible for management, not independent assurance.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.