In the Organising practice, which role is responsible for providing assurance that the project is being conducted correctly?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Assurance

Project Assurance is independent of the Project Manager and provides assurance to the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Team Manager

    Why it's wrong here

    Team Managers are responsible for delivering work packages.

  • Project Assurance

    Why this is correct

    Project Assurance is independent and provides objective oversight.

  • Project Support

    Why it's wrong here

    Project Support provides administrative services.

  • Project Manager

    Why it's wrong here

    The Project Manager is responsible for management, not independent assurance.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.