Which process provides the Project Board with information needed to decide whether to authorize project initiation?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Starting Up a Project

Starting Up a Project (SU) is the pre-project process that produces the Project Brief and initiation Stage Plan, enabling the Project Board to decide whether to proceed with initiation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Starting Up a Project

    Why this is correct

    SU provides the Project Brief for the board to decide on initiation.

  • Controlling a Stage

    Why it's wrong here

    CS is the PM's process for managing a stage.

  • Directing a Project

    Why it's wrong here

    DP is the board's process for making decisions, but the input comes from SU.

  • Initiating a Project

    Why it's wrong here

    IP occurs after authorization to initiate has been given.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.