PRINCE2F PRINCE2 Processes Practice Question
Which process provides the Project Board with information needed to decide whether to authorize project initiation?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Starting Up a Project
Starting Up a Project (SU) is the pre-project process that produces the Project Brief and initiation Stage Plan, enabling the Project Board to decide whether to proceed with initiation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Starting Up a Project
Why this is correct
SU provides the Project Brief for the board to decide on initiation.
- ✗
Controlling a Stage
Why it's wrong here
CS is the PM's process for managing a stage.
- ✗
Directing a Project
Why it's wrong here
DP is the board's process for making decisions, but the input comes from SU.
- ✗
Initiating a Project
Why it's wrong here
IP occurs after authorization to initiate has been given.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.