PRINCE2F PRINCE2 Practices Practice Question

Which THREE statements about the PRINCE2 Risk practice are correct?

⚠ Common exam trap

Test-takers frequently confuse the role of a risk owner with budget authority, leading candidates to incorrectly select Option D, and assuming risk assessment is a one-time event rather than a continuous activity, which makes Option E seem plausible.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The risk register is a management product that records identified risks.

The risk register is a PRINCE2 management product that formally records all identified risks, their status, and related information throughout the project. It is created during the Initiating a Project process and maintained as risks are identified, assessed, and responded to.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The risk register is a management product that records identified risks.

    Why this is correct

    The risk register documents all identified risks and their management.

  • The risk management strategy describes how risks will be managed.

    Why this is correct

    The risk management strategy defines the procedures and approach for risk management.

  • The risk budget is used to fund risk responses.

    Why this is correct

    The risk budget is a sum of money set aside to fund risk responses.

  • Risk owners are responsible for the risk budget.

    Why it's wrong here

    Risk owners manage the risk, but the risk budget is controlled by the project manager.

  • Risks are assessed only during the initiating a project process.

    Why it's wrong here

    Risks are assessed throughout the project, not only during initiation.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO statements about the Risk practice are correct?

medium
  • A.The risk budget is used to fund the project's activities.
  • B.A risk owner must be identified for each risk.
  • C.Only threats are considered as risks.
  • D.The risk register is optional if the project is small.
  • E.The risk management approach defines how risks will be managed.

Why B: PRINCE2 requires that each risk has a named risk owner who is accountable for managing that risk and implementing the planned responses. This ensures clear accountability and proactive risk management throughout the project lifecycle.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.