Courseiva
PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Which report is produced by the Team Manager to inform the Project Manager about progress against a Work Package?

⚠ Common exam trap

PRINCE2F often tests report ownership and audience — candidates mix up Checkpoint Reports (Team Manager to Project Manager), Highlight Reports (Project Manager to Project Board), and End Stage Reports (Project Manager to Project Board at stage end).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Checkpoint Report

A Checkpoint Report is produced by the Team Manager and given to the Project Manager at the frequency defined in the Work Package. It reports progress, status, and any issues against the Work Package, enabling the Project Manager to monitor the stage. It is the standard mechanism for Team Manager-to-Project Manager progress communication.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Checkpoint Report

    Why this is correct

    The Checkpoint Report is the progress report the Team Manager produces at the frequency agreed in the Work Package, covering status, progress, issues and next steps, and sends to the Project Manager. It satisfies the stem's requirement for reporting progress against a Work Package, unlike Highlight or End Stage Reports.

  • ✗

    End Stage Report

    Why it's wrong here

    The End Stage Report summarises progress for an entire management stage, not for a single Work Package. It is produced by the Project Manager for the Project Board at stage boundaries. The temptation arises because it does report progress, but the Team Manager’s specific output for a Work Package is the Checkpoint Report, which provides the detailed, periodic progress update the stem requires.

  • ✗

    Exception Report

    Why it's wrong here

    An Exception Report forecasts deviations from tolerances and is raised by the Project Manager to the Project Board, so it cannot serve as the Team Manager's routine progress communication. It is tempting because it does address progress, but it applies only when a Work Package's tolerances are forecast to be breached, not for regular Checkpoint reporting.

  • ✗

    Highlight Report

    Why it's wrong here

    The Highlight Report flows from the Project Manager to the Project Board, so it cannot satisfy a Team Manager reporting against a Work Package. It is tempting because it genuinely serves progress reporting, but at project level to the Board. A Checkpoint Report is the correct vehicle for Team Manager to Project Manager progress within a Work Package.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.