What is the purpose of the Managing a Stage Boundary (SB) process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To enable the Project Board to approve completion of the current stage and authorize the next
The SB process provides the Project Board with information needed to review the current stage, approve the next stage Plan, and assess the continued viability of the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To produce the Project Plan and Business Case
Why it's wrong here
The Project Plan and Business Case are produced during Initiating a Project, not SB.
- ✓
To enable the Project Board to approve completion of the current stage and authorize the next
Why this is correct
Correct. The SB process produces a Stage Plan for the next stage and an updated Business Case for Project Board decision.
- ✗
To close the project and hand over the product
Why it's wrong here
Closing the project is the purpose of the Closing a Project process.
- ✗
To plan the activities for the current stage in detail
Why it's wrong here
Planning the current stage is part of the Initiating a Project or the previous SB process.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.