Which THREE of the following are components of a Business Case?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Major risks
PRINCE2 specifies that a Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. Expected benefits, major risks, and costs are explicitly listed.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Major risks
Why this is correct
Major risks are included in the Business Case.
- ✗
Project Plan
Why it's wrong here
The Project Plan is a separate product, not part of the Business Case.
- ✗
Risk Register
Why it's wrong here
The Risk Register is a separate management product.
- ✓
Expected benefits
Why this is correct
Benefits are a key component.
- ✓
Costs
Why this is correct
Costs are a component of the Business Case.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.