Courseiva
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

In PRINCE2, who is responsible for defining the project's acceptance criteria?

⚠ Common exam trap

A common mix-up: candidates confuse the Executive's overall accountability for the project with the specific responsibility for defining acceptance criteria, or they mistakenly assign this task to the Project Manager who manages the acceptance process but does not set the criteria.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior User

In PRINCE2, the Senior User is responsible for defining the project's acceptance criteria because they represent the interests of those who will use the project's products and are best placed to specify the quality expectations and measurable conditions that must be met for the project to be accepted. The acceptance criteria are documented in the Project Product Description, which is part of the Business Case, and the Senior User ensures these criteria reflect the users' needs and are achievable.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Executive

    Why it's wrong here

    The Executive is responsible for the Business Case, not acceptance criteria.

  • Project Assurance

    Why it's wrong here

    Project Assurance provides independent oversight but does not define acceptance criteria.

  • Project Manager

    Why it's wrong here

    The Project Manager facilitates but does not define acceptance criteria.

  • Senior User

    Why this is correct

    The Senior User defines the acceptance criteria to ensure the product meets user needs.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which role is responsible for defining the project's acceptance criteria?

easy
  • A.The Project Manager
  • B.The Senior Supplier
  • C.The Executive
  • D.The Senior User

Why D: The Senior User defines the acceptance criteria on behalf of the users.

Variation 2. Which role is responsible for defining the project's acceptance criteria?

easy
  • A.Project Manager
  • B.Executive
  • C.Senior User
  • D.Senior Supplier

Why C: The Senior User is responsible for defining the acceptance criteria as they represent the users who will accept the final product.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.