Correct answer & explanation
✓
Controlling a Stage
When a stage tolerance is forecast to be exceeded, the PM produces an Exception Report (part of Controlling a Stage) and then the Board decides, but the escalation itself occurs within CS. However, the process for creating an Exception Plan is SB. The escalation step is part of CS.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Controlling a Stage
Why this is correct
The PM escalates via an Exception Report during CS.
- ✗
Managing a Stage Boundary
Why it's wrong here
SB produces the Exception Plan after escalation.
- ✗
Directing a Project
Why it's wrong here
The Board receives escalation but does not trigger it.
- ✗
Managing Product Delivery
Why it's wrong here
MP deals with Work Packages, not escalation.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.