Courseiva
PRINCE2 PracticeseasyMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which TWO roles are permanent members of the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Executive

The Project Board consists of the Executive, Senior User, and Senior Supplier. The Project Manager is not a permanent member.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Executive

    Why this is correct

    The Executive is a permanent member.

  • Team Manager

    Why it's wrong here

    The Team Manager is not a member of the Project Board.

  • Senior User

    Why this is correct

    The Senior User is a permanent member.

  • Project Manager

    Why it's wrong here

    The Project Manager attends Project Board meetings but is not a permanent member.

  • Project Support

    Why it's wrong here

    Project Support is not a member of the Project Board.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.