⚠ Common exam trap

PeopleCert often tests the distinction between the Project Manager's role (preparing information and updating plans) and the Project Board's role (authorizing stages), leading candidates to mistakenly think the Project Manager authorizes the next stage.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Update the Project Plan with actuals and forecasts

During the Managing a Stage Boundary process, the Project Manager must update the Project Plan with actuals and forecasts to reflect the current stage's performance and provide a basis for planning the next stage. This ensures the Project Board has accurate information to authorize the next stage or take corrective action.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Authorize the next stage

    Why it's wrong here

    Authorising the next stage is the Project Board's decision, taken after reviewing the End Stage Report and Next Stage Plan; the Project Manager only prepares and submits these products. It is tempting because the Project Manager drives the boundary process, but authority to approve stage continuation rests with the Board.

  • ✗

    Release a Work Package to the Team Manager

    Why it's wrong here

    Releasing a Work Package belongs to Controlling a Stage, where the Project Manager authorises work to the Team Manager; at Managing a Stage Boundary the focus is producing the End Stage Report and Next Stage Plan. It is tempting because work packages are authorised routinely, but that happens during stage execution, not at the boundary.

  • ✗

    Prepare the Project Brief

    Why it's wrong here

    The Project Brief is produced during Starting Up a Project, before the project mandate is developed into a baseline. At Managing a Stage Boundary the Project Manager prepares the End Stage Report and Next Stage Plan for the board, so this action belongs to an earlier process entirely.

  • ✓

    Update the Project Plan with actuals and forecasts

    Why this is correct

    Managing a Stage Boundary requires the Project Manager to update the Project Plan with actuals from the closing stage and forecasts for the next, then prepare the End Stage Report and Next Stage Plan for the board's authorisation decision.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.