- A
Managing risks on a daily basis
Why wrong: Risk management is done by the PM in CS.
- B
Authorizing initiation of the project
Part of DP.
- C
Preparing Highlight Reports
Why wrong: Highlight Reports are prepared by the PM.
- D
Giving ad-hoc direction to the Project Manager
Part of DP.
- E
Authorizing the project closure
Part of DP.
PRINCE2F PRINCE2 Processes Practice Question
This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Authorizing initiation of the project
Option B is correct because the Project Board is responsible for authorizing the initiation of the project during the Directing a Project process. This authorization formally allows the Project Manager to proceed with the Initiation Stage, committing resources and funding. It is a key decision point that ensures the project aligns with corporate or programme strategy before detailed planning begins.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Managing risks on a daily basis
Why it's wrong here
Risk management is done by the PM in CS.
- ✓
Authorizing initiation of the project
Why this is correct
Part of DP.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Preparing Highlight Reports
Why it's wrong here
Highlight Reports are prepared by the PM.
- ✓
Giving ad-hoc direction to the Project Manager
Why this is correct
Part of DP.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Authorizing the project closure
Why this is correct
Part of DP.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse the Project Board's strategic authorization duties with the Project Manager's operational tasks, such as daily risk management or report preparation, leading them to select options that describe lower-level activities.
Detailed technical explanation
How to think about this question
In PRINCE2, the Directing a Project process covers the Project Board's decision-making from project start-up through closure. The Board authorizes each stage boundary, including initiation, and provides ad-hoc direction when the Project Manager requests advice or when tolerances are breached. This ensures the Board maintains control without micromanaging daily activities, preserving the management-by-exception principle.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A junior network technician can log in to a core router but cannot reach the enable prompt or configuration mode. The AAA server is authenticating the login — but the authorisation policy only grants privilege level 1, not 15. Authentication (who you are) is working; authorisation (what you can do) is not.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Processes — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Processes practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Authorizing initiation of the project — Option B is correct because the Project Board is responsible for authorizing the initiation of the project during the Directing a Project process. This authorization formally allows the Project Manager to proceed with the Initiation Stage, committing resources and funding. It is a key decision point that ensures the project aligns with corporate or programme strategy before detailed planning begins.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.