PRINCE2F PRINCE2 Practices Practice Question
What is the purpose of the Product Status Account?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To summarize the status of products in the project
The Product Status Account provides information about the status of products, typically including their version, state (e.g., in development, approved), and configuration records. It is used to report on the state of the project's products.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To update the configuration management system
Why it's wrong here
Updating is done by configuration management, not the Product Status Account itself.
- ✓
To summarize the status of products in the project
Why this is correct
Correct. The Product Status Account provides a summary of product statuses.
- ✗
To approve changes to baselined products
Why it's wrong here
Approval of changes is done by the Change Authority or Project Board.
- ✗
To record the quality review results of a product
Why it's wrong here
Quality review results are recorded in the Quality Register.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.