Who should perform Project Assurance to ensure independence from the Project Manager?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board members (or their delegates)

Project Assurance is independent of the Project Manager and can be performed by individuals from the Project Board or external reviewers.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Board members (or their delegates)

    Why this is correct

    Correct. Project Assurance must be independent and is often performed by Project Board members.

  • Team Manager

    Why it's wrong here

    Team Manager is responsible for delivery, not assurance.

  • Project Support

    Why it's wrong here

    Project Support provides administrative help, not independent assurance.

  • Project Manager

    Why it's wrong here

    Project Manager cannot assure their own work.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.