PRINCE2F PRINCE2 Processes Practice Question
Which THREE of the following are outputs of the Initiating a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk Management Approach
IP produces the PID, which includes the Project Plan, Business Case, and various management approaches. The Project Brief and End Stage Report are not outputs of IP.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risk Management Approach
Why this is correct
Correct: The Risk Management Approach is created in IP.
- ✗
Project Brief
Why it's wrong here
Project Brief is an output of SU.
- ✓
Project Plan
Why this is correct
Correct: The Project Plan is part of the PID.
- ✗
End Stage Report
Why it's wrong here
End Stage Report is produced in SB.
- ✓
Business Case
Why this is correct
Correct: The Business Case is refined and included in the PID.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.