PRINCE2F People: organizations, teams, and leadership Practice Question
Which TWO of the following statements about the Change Authority role are correct?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Change Authority helps to reduce the burden on the Project Board
The Change Authority is an optional role that can be set up to make decisions on change requests within agreed limits, thereby relieving the Project Board from reviewing every change.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Change Authority is appointed by the Project Manager
Why it's wrong here
The Project Board appoints the Change Authority.
- ✓
The Change Authority helps to reduce the burden on the Project Board
Why this is correct
By handling changes within limits, the Board is less burdened.
- ✗
The Change Authority is always a single person
Why it's wrong here
It can be a person or a group.
- ✗
The Change Authority is a mandatory role in PRINCE2
Why it's wrong here
It is optional.
- ✓
The Change Authority can authorize changes within agreed limits
Why this is correct
This is the purpose of the role.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.