Which practice defines the project management team structure and roles?

⚠ Common exam trap

PRINCE2 often tests the distinction between 'Organising' (structure/roles) and 'Plans' (schedules/resources), so the trap here is confusing the definition of team roles with the planning of activities and deliverables.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Organising

The Organising practice defines the project management team structure, roles, and responsibilities, including the project board, project manager, and team manager roles. It establishes the project's organizational hierarchy and accountability lines, ensuring clear authority and communication paths.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Business Case

    Why it's wrong here

    The Business Case practice establishes the justification, benefits, costs and risks that make the project worthwhile; it documents the rationale, not who fills which role. It is tempting because the business case names an executive sponsor, but the project management team structure and role descriptions are defined by the organisation practice.

  • ✗

    Plans

    Why it's wrong here

    The Plans practice covers producing and maintaining the project, stage and team plans, not defining the team structure and role assignments. It is tempting because planning does involve identifying the resources and people needed, and would be correct when the question asks about product-based planning or scheduling rather than roles.

  • ✓

    Organising

    Why this is correct

    The Organising practice defines the project management team structure, role descriptions and the three-project-interests principle. This satisfies the stem by specifying who is accountable, responsible and consulted across the Project Board, Project Manager and Team Manager levels.

  • ✗

    Progress

    Why it's wrong here

    Progress tracks actuals against baselines and forecasts, covering tolerances, checkpoint and end stage reports; it holds no role definitions. It is tempting because progress reporting involves the whole team, but team structure and role responsibilities sit in the organisation practice, which produces the project management team structure and role descriptions.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which practice defines the project management team structure?

easy
  • A.Business Case
  • B.Plans
  • C.Progress
  • ✓ D.Organising

Why D: The Organising practice defines the project management team structure, including roles, responsibilities, and reporting lines. It establishes who is accountable for key decisions and how the team is organized to deliver the project. This is distinct from other practices that focus on justification, planning, or monitoring.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.