Which TWO of the following are types of issue in PRINCE2?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Off-specification

PRINCE2 defines three types of issues: Request for Change, Off-specification, and Problem/Concern. In this question, the correct answers are Off-specification (D) and Request for Change (E). Constraint, Assumption, and Risk are not classified as issue types in PRINCE2; they are considered in other contexts such as the business case or risk register.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Constraint

    Why it's wrong here

    Constraints are not issue types.

  • Assumption

    Why it's wrong here

    Assumptions are not issue types.

  • Risk

    Why it's wrong here

    Risk is a separate concept, not an issue type.

  • Off-specification

    Why this is correct

    This is a type of issue.

  • Request for Change

    Why this is correct

    This is a type of issue.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.