PRINCE2F PRINCE2 Practices Practice Question
Which TWO of the following are types of issue in PRINCE2?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Off-specification
PRINCE2 defines three types of issues: Request for Change, Off-specification, and Problem/Concern. In this question, the correct answers are Off-specification (D) and Request for Change (E). Constraint, Assumption, and Risk are not classified as issue types in PRINCE2; they are considered in other contexts such as the business case or risk register.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Constraint
Why it's wrong here
Constraints are not issue types.
- ✗
Assumption
Why it's wrong here
Assumptions are not issue types.
- ✗
Risk
Why it's wrong here
Risk is a separate concept, not an issue type.
- ✓
Off-specification
Why this is correct
This is a type of issue.
- ✓
Request for Change
Why this is correct
This is a type of issue.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.