Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

A project manager is defining the project's products in the Product Breakdown Structure. A key stakeholder disagrees with the inclusion of a certain product, claiming it is not needed. The project manager believes the product is essential to meet the user requirements. What is the best course of action according to PRINCE2 practices?

⚠ Common exam trap

PeopleCert often tests the misconception that the project manager has authority over product definitions, when in fact the Project Board holds the decision-making power for scope changes, and the Business Case must be updated to justify any such change.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the Business Case to reflect the costs and benefits of including the product, and present it to the Project Board for a decision.

PRINCE2 requires that any change to the project's scope, including the addition or removal of a product, must be formally assessed against the Business Case. The project manager should update the Business Case with the costs and benefits of including the disputed product and then present it to the Project Board, which holds the authority to approve or reject changes to the project's products. This aligns with the 'continued business justification' principle and the 'change control' practice.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate directly to senior management without discussion with the stakeholder.

    Why it's wrong here

    The issue should first be resolved at the project level; escalation is a last resort.

  • Update the Business Case to reflect the costs and benefits of including the product, and present it to the Project Board for a decision.

    Why this is correct

    This follows the PRINCE2 practice of continued business justification and involves the Project Board.

  • Proceed with including the product as the project manager has authority over product definitions.

    Why it's wrong here

    The project manager does not have unilateral authority; decisions about products should be agreed with stakeholders.

  • Remove the product to satisfy the stakeholder, as stakeholder satisfaction is key.

    Why it's wrong here

    Stakeholder satisfaction is important, but the product may be necessary for the project's success; a balanced decision should be made.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.