Who is responsible for maintaining the Business Case throughout the project?

⚠ Common exam trap

PRINCE2 candidates often confuse the Executive's approval authority with the Project Manager's ongoing maintenance responsibility for the Business Case.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Project Manager

The Project Manager is responsible for maintaining the Business Case throughout the project because they manage day-to-day activities, track progress against the Business Case, and provide updated information to the Executive for approval. PRINCE2 assigns the Project Manager the duty of ensuring the Business Case remains viable by monitoring costs, benefits, and risks, and escalating any deviations. This aligns with the 'continued business justification' principle, where the Project Manager is the custodian of the Business Case's ongoing validity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Executive

    Why it's wrong here

    The Business Case is formally owned by the Executive, who is accountable for its approval and ongoing viability; however, the project manager is responsible for the day-to-day task of maintaining and updating the document to reflect actual costs, benefits, and risks. This option is tempting because the Executive does hold ultimate authority over the Business Case and approves any changes to it, but the specific technical requirement in PRINCE2 is that the project manager performs the maintenance activity, not the Executive. The Executive would be the correct choice only if the question asked who is accountable for the Business Case’s content and approval.

  • The Project Manager

    Why this is correct

    The Project Manager is responsible for maintaining the Business Case throughout the project.

  • The Project Support

    Why it's wrong here

    Project Support provides administrative support, not maintenance of the Business Case.

  • The Senior User

    Why it's wrong here

    The Senior User represents the users and defines benefits but does not maintain the Business Case.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.