Which TWO of the following are produced during the Initiating a Project process?

⚠ Common exam trap

PRINCE2 Foundation often tests the distinction between outputs of Starting Up a Project (e.g., Project Brief) and Initiating a Project (e.g., PID), so candidates mistakenly select the Project Brief as a product of the Initiating a Project process.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Initiation Documentation (PID)

The Initiating a Project process in PRINCE2 assembles the Project Initiation Documentation (PID), so option B is correct: the PID is the consolidated baseline of the project's plans, controls, and business case produced at the end of this process. Option D is also correct because the Risk Management Approach is one of the four strategies (with Quality, Configuration Management, and Communication Management Approaches) created during Initiating a Project and then embedded within the PID. Option A, the End Stage Report, is produced during the Managing a Stage Boundary process, not Initiating a Project. Option C, the Project Brief, is a pre-project input produced during Starting Up a Project, and option E, the Checkpoint Report, is produced during stage execution as part of Managing Product Delivery.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    End Stage Report

    Why it's wrong here

    End Stage Reports are produced during Managing a Stage Boundary, at the close of each management stage, not during Initiating a Project. It is tempting because both processes deal with stage-level documentation, but Initiating a Project instead produces the Project Initiation Documentation and the Benefits Management Approach.

  • ✓

    Project Initiation Documentation (PID)

    Why this is correct

    The Project Initiation Documentation is assembled during Initiating a Project, consolidating the business case, project plan, risk and quality approaches into a single baseline. This satisfies the process's purpose of establishing solid foundations before the project proceeds, giving the Project Board the evidence needed to authorise the next stage.

  • ✗

    Project Brief

    Why it's wrong here

    The Project Brief is the input to Initiating a Project, produced during Starting up a Project, so it cannot also be an output here. It is tempting because the Project Brief underpins the PID, but the correct outputs are the Project Initiation Documentation and the Benefits Management Approach.

  • ✓

    Risk Management Approach

    Why this is correct

    The Risk Management Approach is produced during Initiating a Project as part of the PID, defining how risks will be identified, assessed and controlled throughout the project. It is one of the four management approaches established at initiation.

  • ✗

    Checkpoint Report

    Why it's wrong here

    Checkpoint Reports are produced in Managing Product Delivery.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project is in the Initiating a Project process. Which of the following is produced during this process?

medium
  • ✓ A.Benefits Management Approach
  • B.Project Brief
  • C.End Stage Report
  • D.Exception Report

Why A: The Benefits Management Approach is produced during the Initiating a Project process because it defines how the project's benefits will be measured, managed, and realized. This document is created as part of the detailed planning and governance setup that occurs in this process, ensuring alignment with the business case.

Variation 2. Which TWO of the following are produced during the Initiating a Project process?

medium
  • A.Project Brief
  • B.End Stage Report
  • ✓ C.Risk Management Approach
  • ✓ D.Communication Management Approach
  • E.Exception Report

Why C: In PRINCE2, the Initiating a Project process creates the Project Initiation Documentation (PID), and the Risk Management Approach (option C) is one of its component management strategy documents produced during this process. The Communication Management Approach (option D) is likewise a PID component created while initiating the project, defining how information will be exchanged among stakeholders. By contrast, the Project Brief (option A) is an input to Initiating a Project, produced earlier during Starting Up a Project, not an output of this process. The End Stage Report (option B) is produced during Managing a Stage Boundary, and the Exception Report (option E) is produced during Controlling a Stage when tolerances are forecast to be exceeded, so neither belongs to Initiating a Project.

Variation 3. Which TWO outputs are produced during the Initiating a Project process?

medium
  • ✓ A.Project Initiation Documentation (PID)
  • ✓ B.Benefits Management Approach
  • C.Project Brief
  • D.Work Package
  • E.End Stage Report

Why A: The Project Initiation Documentation (PID) (option A) is the primary output of the Initiating a Project process, as it consolidates the business case, project plan, risk, quality, change, and communication approaches into a single baseline document. The Benefits Management Approach (option B) is also produced during Initiating a Project, defining how and when the project's benefits will be measured, reviewed, and realized. The Project Brief (option C) is created earlier in the Starting up a Project process, not during Initiating a Project. A Work Package (option D) is produced during Controlling a Stage when work is authorized to a team, and an End Stage Report (option E) is produced during Managing a Stage Boundary, so neither belongs to Initiating a Project.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.