Which TWO of the following are outputs of the Managing a Stage Boundary process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Stage Plan for the next management stage
Managing a Stage Boundary produces an End Stage Report and a next Stage Plan (which is a Stage Plan for the next management stage). The Project Brief is an output of Starting Up a Project. The Benefits Management Approach is an output of Initiating a Project. The Lessons Report is an output of Closing a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Benefits Management Approach
Why it's wrong here
This is an output of IP.
- ✗
Project Brief
Why it's wrong here
The Project Brief is an output of SU.
- ✓
Stage Plan for the next management stage
Why this is correct
SB produces the Stage Plan for the next stage.
- ✓
End Stage Report
Why this is correct
The End Stage Report is a key output of SB.
- ✗
Lessons Report
Why it's wrong here
The Lessons Report is an output of CP.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.