Which TWO statements about the PRINCE2 Quality practice are correct?
⚠ Common exam trap
Many exam-takers confuse the roles of quality control and quality assurance, leading candidates to incorrectly assign quality control to the project board or quality assurance to the project manager, when in fact the project manager owns quality control and the project board owns quality assurance.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The quality register is used to record planned and completed quality activities.
The quality register is the PRINCE2 management product used to record all planned and completed quality activities, including quality inspections and test results. It provides a log of quality events throughout the project lifecycle, enabling traceability and auditability of quality efforts.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Quality control is the responsibility of the project board.
Why it's wrong here
Quality control is typically performed by the team, not the project board.
- ✗
Quality assurance is performed by the project manager.
Why it's wrong here
Quality assurance is independent of project management; the project manager does not perform it.
- ✓
The quality register is used to record planned and completed quality activities.
Why this is correct
The quality register logs quality activities and their results.
- ✓
The quality management strategy defines the project's approach to quality.
Why this is correct
The quality management strategy is a management product that defines the quality approach.
- ✗
The project product description is a specialist product.
Why it's wrong here
The project product description is a management product, not a specialist product.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.