A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await directions

According to PRINCE2's management by exception principle, if a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The PM cannot exceed tolerance without authorization.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Raise an Exception Report to the Project Board and await directions

    Why this is correct

    When stage tolerance is forecast to be exceeded, the PM must escalate via an Exception Report to the Project Board, which will decide on corrective action.

  • Increase the stage budget by using the project's change budget

    Why it's wrong here

    The change budget is for authorized changes, not for covering tolerance overruns. The PM cannot unilaterally increase the stage budget.

  • Continue with the current plan and report the overrun in the next Highlight Report

    Why it's wrong here

    Continuing without escalation violates management by exception. The PM must escalate immediately.

  • Close the project as the Business Case is no longer viable

    Why it's wrong here

    A cost overrun does not automatically invalidate the Business Case. The Project Board will assess viability.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.