PRINCE2 Practices →hardMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

In the PRINCE2 risk management procedure, which step follows 'Assess'?

⚠ Common exam trap

PRINCE2F often tests the order of the risk management steps—candidates might think 'Communicate' is a sequential step after 'Assess', but it is ongoing.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Plan

The PRINCE2 risk management procedure consists of five steps: Identify, Assess, Plan, Implement, and Communicate. The 'Assess' step involves evaluating the probability and impact of identified risks. The step that follows 'Assess' is 'Plan', where responses to the risks are planned.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Implement

    Why it's wrong here

    Implement is the final step of the PRINCE2 risk procedure, following Plan, not Assess. It is tempting because implementing agreed responses is the natural outcome of assessing risks, but the step immediately after Assess is Plan, where responses are identified, evaluated and assigned to owners.

  • ✗

    Communicate

    Why it's wrong here

    Communicate is a supporting activity running throughout the risk procedure, not the step sequenced after Assess. It is tempting because ongoing communication of risk status is genuinely required, but the procedure's next step after Assess is Plan, which identifies and assigns responses to the assessed risks.

  • ✗

    Identify

    Why it's wrong here

    Identify precedes Assess in the PRINCE2 risk procedure, so it cannot follow it. It is tempting because Identify is a genuine step in the cycle, but the sequence runs Identify, Assess, Plan, Implement, Communicate; the step after Assess is Plan.

  • ✓

    Plan

    Why this is correct

    Planning follows assessment because the PRINCE2 procedure sequences risk identification, then assessment of probability and impact, then planning of responses. The 'Plan' step defines the response actions and owners, satisfying the stem's requirement for the step immediately after 'Assess'.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.