PRINCE2F PRINCE2 Practices Practice Question
Which document is the key output of the Initiating a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Initiation Documentation (PID)
The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, as it defines the project and serves as the foundation for its management.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Plan
Why it's wrong here
The Project Plan is part of the PID but not the key output alone.
- ✓
Project Initiation Documentation (PID)
Why this is correct
The PID is the comprehensive document produced during the Initiating a Project process.
- ✗
Business Case
Why it's wrong here
The Business Case is developed earlier in Starting Up a Project and refined during initiation.
- ✗
Stage Plan
Why it's wrong here
Stage Plans are produced for each management stage, not as the key output of initiation.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.