PRINCE2F PRINCE2 Practices Practice Question
Which THREE of the following are responsibilities of the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Approving Stage Plans
The Project Board provides direction, approves plans, and makes key decisions.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Approving Stage Plans
Why this is correct
The Board approves Stage Plans.
- ✓
Providing direction and control
Why this is correct
The Board directs the project.
- ✓
Deciding on exception situations
Why this is correct
The Board decides on exceptions.
- ✗
Preparing the Project Brief
Why it's wrong here
The Project Manager prepares the Project Brief.
- ✗
Managing day-to-day activities
Why it's wrong here
The Project Manager manages day-to-day activities.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.