Which THREE of the following are responsibilities of the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Approving Stage Plans

The Project Board provides direction, approves plans, and makes key decisions.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Approving Stage Plans

    Why this is correct

    The Board approves Stage Plans.

  • Providing direction and control

    Why this is correct

    The Board directs the project.

  • Deciding on exception situations

    Why this is correct

    The Board decides on exceptions.

  • Preparing the Project Brief

    Why it's wrong here

    The Project Manager prepares the Project Brief.

  • Managing day-to-day activities

    Why it's wrong here

    The Project Manager manages day-to-day activities.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.