Courseiva
PRINCE2 PracticesmediumMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Which TWO of the following are components of the Project Initiation Documentation (PID)?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Business Case

The PID includes the Project Plan and the Business Case. The Risk Register and Issue Register are separate documents. The Lessons Log is created during Starting Up a Project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Lessons Log

    Why it's wrong here

    The Lessons Log is created during Starting Up a Project and is not part of the PID.

  • Business Case

    Why this is correct

    The Business Case is a component of the PID.

  • Issue Register

    Why it's wrong here

    The Issue Register is a separate document.

  • Project Plan

    Why this is correct

    The Project Plan is a component of the PID.

  • Risk Register

    Why it's wrong here

    The Risk Register is a separate document.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.