PRINCE2F PRINCE2 Practices Practice Question
Which TWO of the following are components of the Project Initiation Documentation (PID)?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Business Case
The PID includes the Project Plan and the Business Case. The Risk Register and Issue Register are separate documents. The Lessons Log is created during Starting Up a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Lessons Log
Why it's wrong here
The Lessons Log is created during Starting Up a Project and is not part of the PID.
- ✓
Business Case
Why this is correct
The Business Case is a component of the PID.
- ✗
Issue Register
Why it's wrong here
The Issue Register is a separate document.
- ✓
Project Plan
Why this is correct
The Project Plan is a component of the PID.
- ✗
Risk Register
Why it's wrong here
The Risk Register is a separate document.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.