What is the difference between a Highlight Report and a Checkpoint Report?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Highlight Reports are for the Project Board; Checkpoint Reports are for the Project Manager
Highlight Reports are from PM to Project Board; Checkpoint Reports are from Team Manager to PM.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Highlight Reports are for the Project Board; Checkpoint Reports are for the Project Manager
Why this is correct
Correct.
- ✗
They are the same but with different names
Why it's wrong here
They have different audiences and purposes.
- ✗
Highlight Reports are written by the team; Checkpoint Reports are written by the PM
Why it's wrong here
Highlight Reports are written by the PM; Checkpoint Reports by the Team Manager.
- ✗
Highlight Reports are for stakeholders; Checkpoint Reports are for the Project Board
Why it's wrong here
Checkpoint Reports are for the PM.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.