Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

Which of the following is NOT a role in the PRINCE2 project management team?

⚠ Common exam trap

A common mix-up: candidates confuse the generic term 'Project Sponsor' with the PRINCE2-specific 'Executive' role, leading them to incorrectly select a wrong option like Change Authority or Team Manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Sponsor

The PRINCE2 project management team structure includes the Project Board (Executive, Senior User, Senior Supplier), Project Manager, Team Manager, and optionally the Change Authority. The Project Sponsor is not a defined role in PRINCE2; instead, the Executive role fulfills the sponsorship responsibilities. Therefore, option A is correct as the role that does NOT exist in the PRINCE2 framework.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Sponsor

    Why this is correct

    PRINCE2 defines the Project Board with Executive, Senior User and Senior Supplier roles, plus Project Manager, Team Manager and Project Assurance. 'Project Sponsor' is not a PRINCE2 term; that responsibility maps to the Executive, making this the non-role.

  • ✗

    Change Authority

    Why it's wrong here

    Change Authority is a real PRINCE2 role, appointed by the Project Board to authorise changes within agreed tolerances. It is tempting to reject because it is optional and often delegated, but PRINCE2 defines it as part of the project management team structure.

  • ✗

    Team Manager

    Why it's wrong here

    Team Manager is a genuine PRINCE2 role, responsible for the team's work on a Work Package. It is tempting to reject because it sits below the Project Manager, but PRINCE2 explicitly defines it, so it cannot be the role that is not part of the team.

  • ✗

    Project Manager

    Why it's wrong here

    Project Manager is a core PRINCE2 role, accountable for day-to-day management and delivering the project within agreed tolerances. It is tempting to reject because the Project Board holds ultimate accountability, but the Project Manager is explicitly defined within the project management team.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.