PRINCE2F People: organizations, teams, and leadership Practice Question
Which role is responsible for providing independent assurance to the Project Board that the project is on track?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Assurance
Project Assurance is independent of the Project Manager and provides assurance to the Project Board that the project is being managed correctly and remains viable.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Senior User
Why it's wrong here
The Senior User is part of the Project Board and does not provide independent assurance.
- ✗
Project Support
Why it's wrong here
Project Support provides administrative services, not assurance.
- ✓
Project Assurance
Why this is correct
Project Assurance is an independent role that reports to the Project Board.
- ✗
Project Manager
Why it's wrong here
The Project Manager cannot provide independent assurance because they are responsible for day-to-day management.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.