During the Managing a Stage Boundary process, the project manager produces an End Stage Report for the current stage and a Stage Plan for the next stage. However, the project board rejects the Stage Plan. What is the project manager's next course of action according to PRINCE2?

⚠ Common exam trap

It's easy for candidates to assume the Project Manager can simply revise and resubmit the plan, but PRINCE2 mandates an Exception Report to the board when a stage plan is rejected, as the board must formally decide the project's fate.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Issue an Exception Report to the project board recommending project closure

When the Project Board rejects the Stage Plan during the Managing a Stage Boundary process, the project cannot proceed as intended. PRINCE2 requires the Project Manager to issue an Exception Report to the Project Board, recommending project closure if the plan is not approved, because the project has no authorized plan to continue and the board must decide whether to close or take alternative action.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Revise the Stage Plan and resubmit it to the project board

    Why it's wrong here

    While possible, the immediate action is to report the issue; revision may come later.

  • Escalate to the program or corporate management for a decision

    Why it's wrong here

    The project manager should first use the Exception Report to the project board.

  • Proceed with the next stage as planned, then report to the project board at the next review

    Why it's wrong here

    This ignores the board's rejection and is not allowed.

  • Issue an Exception Report to the project board recommending project closure

    Why this is correct

    This formally documents the issue and allows the board to decide on closure.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.