Courseiva
PRINCE2 Practices →mediumMultiple Select

PRINCE2F PRINCE2 Practices Practice Question

Which TWO of the following are elements of the Business Case?

⚠ Common exam trap

PRINCE2F often tests the specific contents of PRINCE2 documents, causing candidates to confuse elements of the Business Case with those of other management products like the Risk Register or Project Plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Expected benefits

In PRINCE2, the Business Case documents the justification for the project by capturing the expected benefits (option B) — the measurable improvements or value the project is intended to deliver — and the major risks (option C), which are the significant uncertainties that could threaten the achievement of those benefits and must be weighed against them. These two elements are essential because the Business Case must show that the benefits outweigh the risks and costs, supporting the continued viability of the project. The Project Plan (option A) is a separate management product describing schedules, resources, and products, not a component of the Business Case. The Quality Register (option D) and Risk Register (option E) are standalone registers that record quality and risk data respectively; they inform but are not elements of the Business Case itself.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Plan

    Why it's wrong here

    The Project Plan describes products, schedules and resources for delivery; the Business Case contains the justification, expected benefits, costs and risks. It is tempting because the plan informs cost and timeline estimates, but it is a separate management product, not an element of the Business Case itself.

  • ✓

    Expected benefits

    Why this is correct

    Expected benefits quantify the measurable value the project should deliver, forming the justification half of the Business Case alongside costs. PRINCE2 requires them to be stated and baselined so the project board can judge whether continued investment remains worthwhile.

  • ✓

    Major risks

    Why this is correct

    Major risks record the significant uncertainties that could affect delivery of the project's outcomes, and PRINCE2 treats them as a required Business Case element. They let the board weigh potential threats against expected benefits when authorising or continuing the project.

  • ✗

    Quality Register

    Why it's wrong here

    The Quality Register logs quality activities, results and approvals; the Business Case covers benefits, costs, risks and timescales justifying the project. It is tempting because both are PRINCE2 registers, but the Quality Register belongs to the quality theme, not the Business Case's justification content.

  • ✗

    Risk Register

    Why it's wrong here

    The Risk Register records individual risks, their owners and responses; the Business Case summarises key risks as part of its justification. It is tempting because risk information feeds the Business Case, but the register is a distinct risk-theme product, not one of the Business Case's elements.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.