PRINCE2F PRINCE2 Practices Practice Question
Which TWO of the following are elements of the Business Case?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Expected benefits
Expected benefits and major risks are key components of a Business Case in PRINCE2.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Plan
Why it's wrong here
The Project Plan is a separate document, though costs may be summarized in the Business Case.
- ✓
Expected benefits
Why this is correct
Expected benefits are a required component of the Business Case.
- ✓
Major risks
Why this is correct
Major risks are included in the Business Case as part of the risk assessment.
- ✗
Quality Register
Why it's wrong here
The Quality Register is not part of the Business Case.
- ✗
Risk Register
Why it's wrong here
The Risk Register is a separate document; major risks are summarized in the Business Case.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.