Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

In a PRINCE2 project, the Project Manager submits an Exception Report. What is the most likely trigger for this report?

⚠ Common exam trap

Many candidates confuse an Exception Report (triggered by tolerance breach) with an Issue Report or Change Request (triggered by problems or changes within tolerance).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is forecast to exceed the stage cost tolerance

In PRINCE2, an Exception Report is triggered when a forecast indicates that a stage will exceed its agreed tolerance (e.g., cost or time). Option C is correct because exceeding stage cost tolerance is a formal deviation that requires escalation to the Project Board via an Exception Report, as the Project Manager cannot authorize changes beyond tolerance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Project Manager needs to request additional resources within the current stage tolerance

    Why it's wrong here

    Changes within tolerance are managed by the Project Manager without escalation.

  • A team member reports a minor delay that can be accommodated within tolerance

    Why it's wrong here

    Minor delays within tolerance do not require an Exception Report.

  • The project is forecast to exceed the stage cost tolerance

    Why this is correct

    A forecast tolerance breach triggers an Exception Report to the Project Board.

  • The Senior User requests a change that does not affect the Business Case

    Why it's wrong here

    A change request would be handled via Change Control, not an Exception Report.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.