During the Managing a Stage Boundary process, the Project Manager creates the Stage Plan for the next stage. Who approves this Stage Plan?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board

The Project Board approves the Stage Plan for the next stage, allowing the project to proceed. This is part of the exception-driven decision-making.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The Project Manager creates the Stage Plan but does not approve it.

  • Senior Responsible Owner

    Why it's wrong here

    The SRO is part of the Board, but approval requires the Board's collective decision.

  • Senior Supplier

    Why it's wrong here

    Approval is a collective decision of the full Project Board.

  • Project Board

    Why this is correct

    The Project Board approves the Stage Plan before the next stage can begin.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.