PRINCE2F People: organizations, teams, and leadership Practice Question
During the Managing a Stage Boundary process, the Project Manager creates the Stage Plan for the next stage. Who approves this Stage Plan?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Board
The Project Board approves the Stage Plan for the next stage, allowing the project to proceed. This is part of the exception-driven decision-making.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Manager
Why it's wrong here
The Project Manager creates the Stage Plan but does not approve it.
- ✗
Senior Responsible Owner
Why it's wrong here
The SRO is part of the Board, but approval requires the Board's collective decision.
- ✗
Senior Supplier
Why it's wrong here
Approval is a collective decision of the full Project Board.
- ✓
Project Board
Why this is correct
The Project Board approves the Stage Plan before the next stage can begin.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.